Project Overview

The Cabrini Hospital, in Malvern, Victoria, was opened in 1948.
Over the years AAH has been engaged on numerous occasions to assist with refurbishments.

Scope of Works

  • Removal of asbestos contaminated soil
  • Removal of rubbish
  • Removal of asbestos contaminated concrete sheets
  • Removal of asbestos contaminated vinyl tiles
  • Removal of asbestos pipe lagging
  • Removal and reinstatement of ceiling tiles
  • Floor grinding to various areas back to slab ready for reinstatement
  • Removal of cement sheet baffle walls above duct
  • Removal of asbestos woven blanket
  • Removal of SMG insulation from pipework
  • Sealing of exposed materials
  • Removal of Styrofoam insulation from ductwork
  • Removal of asbestos contaminated debris on ducting
  • Transport & disposal of all waste to EPA licensed facilities
Ready to chat? Call our team today on (03) 9729 0066