Project Overview

In February 2019, AAH was awarded works at Werribee Train Station to remove mould and lead paint from the internals of the station.

Scope of Works

  • Remove mould and lead paint from affected surfaces in the cleaners room, plant room and staff room
  • Works to be completed during normal work hours

Critical Factors/Challenges

The challenges and critical factors to successfully complete the works were.

  • Werribee Station is a busy location and a central hub for many lines with a large number of members of the general public commuting around the works areas
  • All personnel had to be RIW accredited
  • Waste had to be removed via a publicly shared pathway
  • Works had to be completed with minimal disruption to usual station operations

Outcomes

  • Works were successfully completed with minimal disruption to station operations
  • Temporary fencing was set up on the station concourse around the works area to ensure the public were kept at a safe distance
  • Areas were fully cleaned/decontaminated which allowed underlying water leaks issues to also be fixed
  • Completed on time and within budget with no incidents
Areas were fully cleaned/decontaminated which allowed underlying water leaks issues to also be fixed