Project Overview
Archive Centre, Spotswood is a VicTrack asset property that AAH was contracted to remediate. Works included asbestos removals and floor grinding throughout the property
Scope of Works
- Remove all asbestos containing materials up to ‘non structural disturbance’
- Grind up to 100m2 of contaminated flooring
- Encapsulate divets to deep to grind
- Remove contaminated ceilings and grid work
Critical Factors/Challenges
The challenges and critical factors to successfully complete the works were.
- Guaranteed deadline, “works must be completed within 5 weeks”
- Additional concrete had to be laid to encapsulate old track area within the existing time restraints
Outcomes
- All works were completed within timeframe
- Met all of client’s requirements
- Works were completed in 3 sections
- 0 safety incidents
- Over 800 man hours worked
- Location Spotswood, Victoria
- Completion July, 2019
- Services
Commercial & Industrial Asbestos Removal
Floor Grinding
Waste Removal & Transport
Over 800 man hours worked to complete the job with 0 safety incidents